Work Description
All works necessary for construction and installation of 11 (eleven) transmission line works
at 230, 138 and 115 kV and a total length of 432.8 km-C, and 10 (ten) transformation substation
works with voltages of 400, 230, 138 and 115 kv and a total capacity of 1533.3 MVA, 18MVAR, of
inductive type, and 30 (Thirty) high tension feeders located on Coahuila, Chihuahua, Durango y Baja
California Norte, Mexico.
Kind of Responsibilities
Supply, assembly, resting and commissioning.
|